City’s Conglomerate Paving Project
Update as of 11/21/2025
The Conglomerate Paving Project, which includes street paving work, select sidewalk repairs, and asphalt concrete (AC) berm repairs, began on November 12.
Project Scope Includes:
- Asphalt overlay
- Spot pavement repairs and micro-surfacing
- Pavement rehabilitation and reconstruction
- Sidewalk, AC berms, and ADA ramps improvement
Completed Work:
- 10th Avenue between Mission Street and Junipero Street
- 6th Avenue between Guadalupe Street and Carpenter Street
Current Work:
- Torres Street between 2nd Avenue and 4th Avenue is near completion
Upcoming Work:
November 24–26: Pavement Patch Work
Dig-out work in preparation for the upcoming Street Micro- surfacing in a few months:
- Monterey Street (North End to Second Avenue)
- Santa Fe Street (Third Avenue to Fourth Avenue)
- Santa Rita Street (North City Limits to Second Avenue)
- 3rd Avenue (Dolores Street to Mission Street)
- Monte Verde Street (Second Avenue to Fourth Avenue)
- Perry Newberry Way (Fourth Avenue to Sixth Avenue)
- Guadalupe Street (Second Avenue to Third Avenue)
- Guadalupe Street (Fifth Avenue to Sixth Avenue)
- Lobos Street (First Avenue to Second Avenue)
- Forest Road (Ocean Avenue to Seventh Avenue)
- Pine Ridge Way (Forest Road to Turnaround)
December 2–12: AC Overlay Work (Tentative Schedule, Weather Permitting)
- Ocean Avenue between Highway 1 and Carpenter Street
Please Note:
Updates to the schedule, work sites, potential weather-related delays, and a map of all paving areas will be posted on the City website.
Traffic & Access Information:
- Heavy equipment will be in use — please avoid the area if possible.
- Temporary lane closures and detours will be in place to assist with traffic circulation.
- Local residents and businesses will be provided with access, but please expect delays and exercise caution when traveling through the work zones.
- Limited or No Street Parking in work zones.
We appreciate your patience and cooperation during this construction operation. For your safety and the safety of workers, please follow all detour signs and traffic control signage within and adjacent to the work zones.
Contact Information:
- City Project Manager: Shari Carlet, (831)-427-7665
- Contractor: Coastal Paving and Excavating, Casey Kenyon, (831)-920-9396
AC Overlay Completed: Torres Street (2ND to 3RD Avenues)
AC Overlay Completed: Torres Street (3RD to 4th Avenues)