City’s Conglomerate Paving Project
Update as of 12/15/2025
Conglomerate Paving Project Update
The Conglomerate Paving Project, which includes street paving work, select sidewalk repairs, ADA ramps, and asphalt concrete (AC) berm repairs, began on November 12.
Completed Paving Work:
Ocean Avenue between Highway 1 and Carpenter Street
10th Avenue between Mission Street and Junipero Street
6th Avenue between Guadalupe Street and Carpenter Street
Torres Street between 2nd Avenue and 4th Avenue
Completed Dig-Out Work:
Perry Newberry Way (4th Avenue to 6th Avenue)
Lobos Street (1st Avenue to 2nd Avenue)
Guadalupe Street (2nd Avenue to 3rd Avenue)
Guadalupe Street (5th Avenue to 6th Avenue)
Current Work: December 15-19
Ocean Avenue (Hwy. 1 to Carpenter St.): AC berms, Raising irons, Traffic Loops
Ocean and San Antonio Avenues Intersection: ADA Ramps
Torres Street (2nd Ave and 3rd Ave): AC Berms
Upcoming Work: (Weather Permitting)
January 5-23: Street Reconstruction, AC Overlay, Dig-Outs
Ocean and San Antonio Avenues Intersection: Street Reconstruction
San Antonio Avenue (4th Ave to Ocean Ave): AC Overlay, Dig-outs
San Antonio Avenue (Ocean Ave to 8th Ave): AC Overlay, Dig-outs
Perry Newberry Way (4th to 6th Ave): Drainage Ditch
Please Note:
Updates to the schedule, work sites, potential weather-related delays, and a map of all paving areas will be posted on the City website.
We appreciate your patience and cooperation during this construction operation. For your safety and the safety of workers, please follow all detour signs and traffic control signage within and adjacent to the work zones.
*Update as of 12/15/2025
Contact Information:
- City Project Manager: Shari Carlet, (831)-427-7675
- Contractor: Coastal Paving and Excavating, Casey Kenyon, (831)-920-9396
AC Overlay Completed: Torres Street (2ND to 3RD Avenues)
AC Overlay Completed: Torres Street (3RD to 4th Avenues)